1. High-strength non-shrink grout material grouting 24 h before take measures to protect the grouting parts from direct sunlight or other heat radiation. 2. Take appropriate measures to cool, and high-strength non-shrink grout material and equipment in contact with concrete foundation slab temperature is not more than 35 ℃. 3. Slurry into the mould temperature should not be greater than 30 ℃. 4. High-strength non-shrinkage grouting material should be timely moisture curing measures after grouting.