The first part of foundation treatment
1. Use grinding machine to conduct a comprehensive and detailed burnish. Let damaged, sand, bonding, cracking, empty drum position fully exposed; And will float sand old epoxy mortar, concrete, etc. Need used epoxy floor paint renovated
please telephone contact! We will make quotation according to the actual circumstance of the ground you!
2, looseness, crack, the ground of delaminating, must be thoroughly polished to compacted layer, ensure the adhesive force of epoxy primer.
3。 Will base on the surface of the float ash, pollutants, such as clean up garbage, and ensure the clean degree of the basic surface.
4。 Will handle the ground clean
inspection method: after treatment, floor surface smooth, dense, dry, no oil, loose and not brittle particles, can take the next step of construction.
expansion joints, cracks, empty drum loose ground, special treatment of the old epoxy
1. Of cracking parts adopt after cutting slices cut into V groove, to repair the bridge, with high strength epoxy mortar again after being cured by hand grinding machine is flat and level.
2, the empty drum, wipe out the old epoxy ground of loose part, if the groove is deeper, need to use high strength epoxy mortar repair, to fully cure the cause grinding machine is flat and level.
3。 All special parts repair processing, clean it again. Test method of
a. Treatments of special positions above is the whole floor paint one of the most important aspects of the use lifespan, otherwise will result in the crack of the floor.
b。 After treatment, the relatively flat on the ground, mend close-grained, hard.
c。 The ground clean, according to the requirements of construction construction epoxy primer.
1, the second part of epoxy mortar layer in clean floor, epoxy resin and quartz sand in the correct ratio of mixture, using batch of uniform trowel scraping knife on the ground, to increase the combination between coating and surface, and further adjust the roughness of the ground;
2 times, according to actual needs, construction, smooth and no holes, no batch of knife is printed and sanding shall prevail.
inspection method: to make completely flat on the ground without holes, there is no batch knife printing and sanding India for coating construction.
inspection method: to make completely flat on the ground with no holes, no batch knife after printed and sanding, can start construction epoxy coating.
1, in the third part epoxy coating epoxy resin primer cured completely, and ensure that the floor clean without sundry adhesion. Epoxy resin and curing agent abrasive powder in the correct proportion mixed stirring,
2, using trowel uniform full again, ensure no holes, no batch printing.
inspection methods: flat on the ground, no batch knife, no holes, before construction epoxy layer
the fourth part epoxy layer 1, keep the floor clean before construction, if there are any debris to remove
2, finishing coat of epoxy paint material part first mix; Add curing agent mixed in proportion, and fully mixing
3, materials used drum will be evenly coated.
4, according to the needs of construction or 2 times again.
5, if the paint is self-leveling floor, need a trowel construction.
inspection method: the ground colour and lustre is uniform, no flow, no pinhole, smooth, level off. Epoxy floor paint construction
note
1, the surface must be polished well, otherwise it may cause the adhesive force of epoxy primer not
2, don't cross the construction, so as not to affect construction quality
3, each layer completely cured before the construction activity.
4。 The weather is too hot, too cold, humidity is too big to stop the construction.